Centerra Gold – Endako Mine

Date: September 2020 – November 2022
Client: Centerra Gold
Frost Group was contracted by Centerra Gold (Thompson Creek Metals) to Haul 475,000 Tons of Potential Acid Generating (PAG) Rock at the Endako Mine to the area adjacent to the tailings pond.
Frost Group was also contracted by Centerra Gold (Thompson Creek Metals) to Load, Haul and Place 413,000 m3 of tailings to re-contour a tailings pond as part of the Endako Mine reclamation.
Frost Group was also contracted by Centerra Gold (Thompson Creek Metals) to Load, Haul and Place 413,000 m3 of tailings to re-contour a tailings pond as part of the Endako Mine reclamation.